This is the AIRS, AMSU-A, and HSB weekly operations status report for Friday, August 14, 2026 (the end of week 1267 of the Aqua mission). AIRS: The AIRS instrument remains healthy with all voltages, currents, and temperatures as expected. AMSU-A1: AMSU-A1 is healthy except for channels 4, 5, 6, and 7. AMSU-A2: AMSU-A2, which provided channels 1 and 2 of the AMSU-A suite, suffered a non-recoverable loss of power on September 24, 2016 and is no longer operational. HSB: HSB has been non-operational since February 2003 due to a scanner anomaly. Instrument activities since previous report: There were no instrument activities this past week. Upcoming events: 1) An Aqua Point for Power Test is scheduled for Wednesday, August 19. Here is the timeline (UT): 231/15:04:00 AIRS in READY mode 231/15:05:07 Slew begins (yaw amount 20.0 degrees) 231/15:15:56 Slew complete 231/15:21:56 Return slew begins 231/15:32:45 Return slew complete 231/15:34:00 AIRS back in OPERATE mode 2) An AIRS guard test is scheduled for Sunday, August 23. Here is the timeline (UT): 235/22:52:00 AIRS Guard Test begins (AIRS in CHECKOUT mode) 235/23:19:00 AIRS back in OPERATE mode Daily plots of noise levels for each AIRS channel are available on the AIRS webpage at https://airs.jpl.nasa.gov/mission/instrument-operations/. A link there currently points to where the files are hosted at https://airsnrt.jpl.nasa.gov/nedt_trends/html/airs_channel_nedt_trends.html. For each channel there are plots for the whole AIRS mission and for the last 2 months. Going forward, weekly Ops status updates will be archived at the same webpage above, and are hosted at https://airsnrt.jpl.nasa.gov/report/latest and https://airsnrt.jpl.nasa.gov/report/archive/. ================================================================== William Mathews - AIRS Instrument Operations NASA / Jet Propulsion Laboratory