This is the AIRS, AMSU-A, and HSB weekly operations status report for Friday, November 24, 2023 (the end of week 1125 of the Aqua mission). Note that there were changes to the test schedule that appeared in last week's report. Specifically: - The C9-space-B-gains and C9-space-Optimum-gains tests that had been scheduled for Tuesday, November 14 have been re-scheduled to Monday, November 20. - The C9-OBC-B-gains and C9-OBC-Optimum-gains tests that had been scheduled for Wednesday, November 15 have been re-scheduled to Tuesday, November 21. AIRS: The AIRS instrument remains healthy with all voltages, currents, and temperatures as expected. AMSU-A1: AMSU-A1 is healthy except for channels 4, 5, 6, and 7. AMSU-A2: AMSU-A2, which provided channels 1 and 2 of the AMSU-A suite, suffered a non-recoverable loss of power on September 24, 2016 and is no longer operational. HSB: HSB has been non-operational since February 2003 due to a scanner anomaly. Instrument activities since previous report: Four AIRS special calibration tests ran on Monday and Tuesday, November 20 and 21. Here is the timeline (UT): Monday, November 20: C9 Scan Profile Rotation to Space View Test, B-only gains 324/09:05:00 AIRS put into READY mode 324/09:45:00 AIRS back in OPERATE mode C9 Scan Profile Rotation to Space View Test, Optimum gains 324/22:16:00 AIRS put into READY mode 324/22:54:00 AIRS back in OPERATE mode Tuesday, November 21: C9 96 OBC View 96 B-only gains 325/09:46:00 AIRS put into READY mode 325/10:26:00 AIRS back in OPERATE mode C9 96 OBC View 96 Optimum gains 325/22:58:00 AIRS put into READY mode 325/23:36:00 AIRS back in OPERATE mode An AIRS guard test ran on Wednesday, November 22. Here is the timeline (UT): 326/22:07:00 AIRS Guard Test begins (AIRS in CHECKOUT mode) 326/22:34:00 AIRS back in OPERATE mode MODIS Lunar Calibration #225 was executed on Friday, November 24. Here is the timeline (UT): 328/16:57:00 AIRS put into READY mode prior to Lunar Cal 328/17:22:00 AIRS back in OPERATE mode Upcoming events: 1) An AIRS photometric calibration test is planned for Thursday, December 7. This activity has not been scheduled yet. Daily plots of noise levels for each AIRS channel are available on the AIRS webpage at https://airs.jpl.nasa.gov/mission/instrument-operations/. A link there currently points to where the files are hosted at https://thunder.jpl.nasa.gov/nedt_trends/html/airs_channel_nedt_trends.html. For each channel there are plots for the whole AIRS mission and for the last 2 months. Going forward, weekly Ops status updates will be archived at the same webpage above, and are hosted at https://airsteam.jpl.nasa.gov/report/latest and https://airsteam.jpl.nasa.gov/report/archive/. William Mathews - AIRS Instrument Operations NASA / Jet Propulsion Laboratory